Road Work Information:
We will be buggy groove paving 10/22/2025 on 900E between 1000N-400N from 7:30am-4:30pm this will be a moving operation, and flaggers will be helping direct traffic, please use caution when traveling this area.
Crews will be buggy groove paving 10/22/2025 on 900E between 1000N-400N from 7:30am-4:30pm this will be a moving operation, and flaggers will be helping direct traffic, please use caution when traveling this area.
Contractor E&B will begin Paving Operations to the following roads:
Wednesday October 22nd
150N between SR57-75E
Thursday October 23rd
75E between 150N-250N
Friday October 24th
200N 75E-200E
Flaggers will be there to help direct traffic, please use caution when traveling this area.