Commissioners close a road for mining and get an Annex update

        The Daviess County Commissioners gave approval for Solar Sources to temporarily close and mine through County Road 350 N, from County Road 350 E for about a 1/2 mile.  The Commissioners also approved widening CR 450 N by four feet between Edwardsport Road and the Perdue Mill.  

       During the report on the Annex construction, the Commissioner were holding fast to a June 5 completion date for the new building, but Owners Representative Mike Schapker said that deadline is becoming less viable due to problems with suppliers and contractors.  The Commissioners did learn that the construction of the Annex is still running under budget. 

       At the end of the meeting, County Auditor reminded the public that a recording of County Commissioners and County Council meetings can be found on the County’s website by the end of the day the meeting occurred.   The County’s website can be found at www.daviess.org